An arch-shaped steel bridge in the Himalayas will be the world’s highest bridge, stretching 35 metres taller than the Eiffel Tower when construction completes in 2016.

Built over the Chenab River in northern India, the structure’s height will surpass that of the current railway bridge record held by China. That bridge, straddling the Beipanjiang River, is 275 metres in height compared with the expected height of 359 metres Indian engineers are aiming for.

“It is an engineering marvel. We hope to get this bridge ready by December 2016,” a senior Indian Railways official told AFP.

The 1,315-metre long bridge will use up to 25,000 tonnes of steel and is costing the Konkan Railway Corporation, a subsidiary of state-owned Indian Railways, an estimated $92 million.

The structural concept sees a two-ribbed steel arch flanked by concrete approach viaducts on either side. The chords of the trusses are sealed steel boxes, filled with concrete to assist in controlling wind-induced forces on the bridge.

Chenab River Bridge

The main arch is being erected using two cable cranes attached on either side of the river which are secured on enormous steel pylons. The cable cranes are the largest in the world.

One of the biggest challenges involved was constructing the bridge without obstructing the flow of the river. Approach roads had to be constructed just to reach the foundations of the bridge.

Continuous construction has enabled the number of bearings to be minimised, particularly on the approach viaduct. This reduces maintenance and inspection requirements and will provide a smoother ride across the bridge.

“The design would ensure that it withstands seismic activities and high wind speeds,” the Indian Railways official added.

Norway-based Force Technology Laboratory conducted several wind tunnel tests to understand the effects of wind speed, static force coefficients and gust buffeting. The bridge has been designed to resist wind speeds of up to 260 kilometres per hour.

The bridge will be made largely of steel, as the material is more economical and is able to resist temperatures of -20 Celsius as well as potentially high wind speeds. The Jammu and Kashmir region witnesses frequent terrorist attacks. To enhance safety and security, the bridge will be made of 63 millimetre-thick special blast-proof steel. The concrete pillars of the bridge are also designed to withstand explosions.

The massive steel arch is the first of its kind in India. The country has no codes or design guidance for such massive structures. The Indian Railway Standards (IRS) is primarily intended for simply supported bridges with spans up to 100 metres (although these have been successfully used for higher spans up to 154 metres). The engineering team is therefore drawing on experiences from similar projects around the world and following design best practices.

The deck of the bridge is partly straight and partly curved. It is located on a transition curve with changing radius. Construction is therefore being carried out in stages following the gradual change in the alignment. This is the first time a bridge is being constructed incrementally on a transition curve.

Chenab River Bridge

Credit: Daily Mail

Work on the bridge started in 2002 but safety and feasibility concerns, including the area’s strong winds, saw the project halted in 2008 before being green-lit again two years later.

The bridge will connect Baramulla to Jammu in the Himalayan state with a travel time of six-and-a-half hours, almost half the time it currently takes.

Design and construction of the bridge was awarded to a joint venture of Afcons Infrastructure, Ultra Construction & Engineering Company of South Korea and VSL India in 2004.

When completed in 2016, it is expected to have a lifespan of 120 years.